Drivers in the East will have benefited from up to £28.5million in road improvements by the end of March.

This is the value of work either beginning or already taking place on the Highways Agency’s regional network in the run up to the end of the financial year (April 2015), with completion dates varying depending on the length of each scheme.

The focus of the work has been to improve safety and increase the capacity of roads to help ease congestion and ensure better journey experiences across the East region’s busiest roads.

The organisation that looks after the country’s major roads is facing a transformative year in 2015.

By the end of March, in the East alone, the Highways Agency will have invested up to £52.4m in roads renewal, £7.6m in renewing structures, £2m in technology and £28.5m in improvement work.

Highways Agency East Regional Director, Catherine Brookes, said: “This is really good news for road users across the East because it will ultimately mean less congestion, more reliable journey times and improved safety. Vast amounts of money are being invested in roads – that inevitably means more roadworks, but for every scheme we work on there will be an improvement for drivers.

“We are well aware of how frustrating roadworks can be to motorists – but I would like to reassure everyone that all our work is planned very carefully to cause as little disruption as possible. Some is inevitable – and we ask for drivers’ cooperation while the improvements are carried out.”

Since April, works have begun on the pinch point projects on the A1 roundabout at Black Cat, A14 Histon to Girton, A1(M) at Welwyn and the A1/A47 Wansford.

Other works include:

- Resurfacing the A14 westbound between junction 31 and 26

- Average speed cameras have been installed on the A120 at Pellens Corner

- Resurfacing improvements have begun on the A421 Bedford southern bypass, with eastbound completed

- The A5 southbound at Milton Keynes has been resurfaced

- Bridge maintenance work has been completed on the A47

- Improvement work on the A1(M) at Sawtry was completed

- A138 Chelmer Viaduct replacement work has begun

- Improvement work on the A12 at Lowestoft and Ipswich

- Safety measures on the A12 in Suffolk and Essex

- Maintenance work on the A12 between Essex and Ipswich involving renewing the road surface and repairing drainage

- Barrier replacement work on the A14 at Huntingdon

- Safety improvements on the A47 at Walsoken and on the A120 at Houchins Lane.